Transport Minister demands action over Menai Bridge saga


November 23, 2026 - 162 views

Repairs to the Menai Suspension Bridge have suffered another major setback, with completion now pushed back until autumn 2027, at least six months later than previously expected.

The announcement has prompted an angry response from the Welsh Government, which has described the continuing disruption to the historic crossing between Anglesey and the mainland as unacceptable.

Contractors UK Highways A55 Ltd have identified unexpected water ingress affecting steelwork beneath the bridge deck.

The problem, which was not apparent during earlier inspections, has prevented the planned protective paint system from being applied reliably. Contractors have rearranged the remaining work while identifying a suitable alternative treatment.

The setback adds to years of disruption at the 200-year-old bridge, which was initially closed to traffic in October 2022 following serious concerns about its structural safety.

Although the crossing has since reopened, restrictions have remained in place while essential repairs and strengthening work continue.

Deputy Minister for Transport Mark Hooper said: “People have put up with delays and inconvenience on this bridge for too long which is why this government has acted swiftly to get going on a third Menai crossing.”

He added: “I was extremely disappointed and frustrated to learn from the contractors that their programme of repairs, which has been beset by numerous delays, will be delayed once again.”

Mr Hooper has written to the Chief Executive of Equitix, which oversees UK Highways A55 Ltd, demanding an urgent meeting and assurances that the revised timetable will be met.

The bridge will remain open to vehicles weighing up to 7.5 tonnes, with the weight restriction continuing throughout the refurbishment.

Traffic management measures are expected to be removed for the remainder of 2026, although further restrictions may be necessary as work progresses.

The continuing problems have renewed concerns about the resilience of transport links between Anglesey and the mainland, particularly when disruption affects the Britannia Bridge, which carries the A55.

The Welsh Government says it is progressing development work on a proposed third Menai crossing, alongside improvements intended to make the Britannia Bridge more resilient.

UK Highways A55 Ltd is expected to publish a further explanation of the engineering difficulties and revised timetable.

Ministers insist that safety remains the priority and have warned that no further avoidable slippage will be acceptable.